Noida stalled projects registry: Authority orders faster deeds
36 stalled housing projects in Noida have paid ₹561.35 crore under the state's relief package. On 5 September 2026 the Authority's board ordered pending registries sped up and warned 23 builders over the remaining 75%.

₹561.35 crore. That is what 36 stalled housing projects in Noida have paid the Noida Authority so far under Uttar Pradesh's relief package for stuck projects, the Authority's board was told at its 223rd meeting on Friday, 5 September 2026. The board, chaired by Infrastructure and Industrial Development Commissioner Deepak Kumar at the Authority's Sector 96 office, directed officials to clear pending registries in those projects faster. It also sent notices to 23 projects that paid their first instalment but have not cleared the remaining 75% of what they owe. For anyone waiting on a Noida stalled projects registry, that pairing of a push and a warning is the news.
How the Noida stalled projects registry package works
The package goes back to December 2023, when the state cabinet accepted the recommendations of the committee headed by former NITI Aayog chief executive Amitabh Kant on legacy stalled projects. At the time, Business Standard reported that around 190 group housing projects across Noida and Greater Noida owed the two authorities roughly ₹32,000 crore, with more than a lakh flats undelivered.
The mechanics are simple on paper. Interest for the Covid "zero period" is waived and the developer's dues are recomputed. A developer who pays 25% of the recomputed amount gets permission to register completed flats, and the Authority allows registries in proportion to the money received. The balance follows in instalments. Commercial, sports and entertainment projects were kept out, which is why the Sports City parcels in Sectors 150, 151 and 152 have followed a separate route through the Supreme Court and the Authority's 222nd board meeting in April 2026.
The 5 September figures show how far that has come in Noida: 36 projects in, ₹561.35 crore paid, 23 of them still short of the full amount.
What else the board decided on 5 September
- A corpus fund for civic upkeep. The board approved a standard operating procedure for a One-Time Lease Rent Corpus Fund. The idea is that one-time lease rent receipts go into a fund whose income pays for water supply, sanitation, public health and maintenance, rather than being spent as they arrive.
- Sub-lease deeds for cooperative societies. A tripartite sub-lease deed framework was cleared for cooperative housing societies, a document that members of older societies have struggled to get executed.
- Land compensation up 53%. Farmers who give land and opt for a 5% developed plot will now get ₹6,459 per sq m, up from ₹4,224. For land bought by mutual agreement the rate goes from ₹5,324 to ₹6,459 per sq m. Rates for New Noida (the DNGIR area) were brought in line with the Greater Noida and Yamuna Expressway authorities.
- Waste to energy. A 100-tonne-a-day waste-to-energy plant was approved for Sector 145.
If you own a flat in one of these projects
Ask the builder's customer desk for two documents: the Authority's registry permission letter for your tower, and the count of flats that letter covers. Because registries are released in proportion to dues paid, a project that has paid 25% may have permission for a quarter of its completed flats, not all of them. Your flat is either inside that number or it isn't, and the builder knows which.
Before the sub-lease deed is executed you will pay stamp duty at 7% (6% for a woman buyer on a flat worth up to ₹1 crore) plus a 1% registration fee, worked out on the higher of your agreement value and the circle rate. Check the amount on the Uttar Pradesh stamp duty calculator and budget for it now; builders rarely give notice of more than a few weeks.
If you're buying resale in one
A resale flat in a stalled project is cheap for a reason. Without a registered sale deed the seller cannot pass you a clean title and most banks will not lend against it. Insist on three things before paying a token: the registry permission letter covering that specific flat, the tower's occupancy certificate, and a no-dues certificate from the builder for the seller's account. If any of the three is missing, the discount is not a discount.
What people get wrong
A registry is read as the end of the story. It transfers ownership of your flat to you, which matters enormously, but it does not finish the unbuilt tower next door, fund the pending club, or guarantee the developer pays the remaining 75%. The notices to 23 projects are the Authority's way of saying the second part is not optional. If a developer stops paying, the proportional permission stops with it, and the flats still unregistered stay unregistered.
The Authority did not publish a project-wise list with the board note. Until it does, the registry permission letter in the builder's hands is the only reliable test of whether a given tower is covered. Buyers who would rather avoid the question altogether can filter for ready-to-move projects in Noida and check the current asking rates by sector before negotiating.
Sources
- The Pioneer, 6 September 2026: Noida hikes farmers' land compensation to ₹6,459 per sq m
- H4E News: Noida Authority 223rd board meeting, faster registries for stalled projects
- Business Standard, December 2023: Decks clear for house registry in stuck projects in Noida, Greater Noida
- Deccan Herald, December 2023: UP government approves Amitabh Kant committee proposals
Frequently asked questions
What did the Noida Authority decide about stalled projects on 5 September 2026?
At its 223rd board meeting the Authority noted that 36 stalled projects had paid ₹561.35 crore under the state's relief package, directed officials to speed up pending registries in those projects, and issued notices to 23 projects to pay the remaining 75% of their dues.
How does the 25% dues scheme for Noida registries work?
Under the package approved in December 2023 on the Amitabh Kant committee's recommendations, interest for the Covid zero period is waived, dues are recomputed, and a developer who pays 25% of the recomputed amount gets registries opened for completed flats in proportion to the payment. The balance is paid in instalments.
How do I check whether my flat can be registered?
Ask the builder for the Noida Authority's registry permission letter for your tower and the number of flats it covers. Registries are released in proportion to dues paid, so not every completed flat is covered at once. The Authority has not published a project-wise list with the September board note.
Is it safe to buy a resale flat in a stalled Noida project?
Only if the registry permission letter covers that flat, the tower has an occupancy certificate and the seller has a no-dues certificate from the builder. Without a registered sale deed you get no clean title and most banks will not lend against the flat.
Sources: The Pioneer, 6 September 2026: Noida hikes farmers' land compensation to ₹6,459 per sq m · H4E News: Noida Authority 223rd board meeting, faster registries for stalled projects · Business Standard, December 2023: Decks clear for house registry in stuck projects in Noida, Greater Noida · Deccan Herald, December 2023: UP government approves Amitabh Kant committee proposals